Gravel: cubic yards versus tons

One supplier quotes you a price per ton, the next quotes per cubic yard, and you are trying to work out which is cheaper for the same pile of stone. They measure different things — weight against volume — and converting between them takes one number that changes with the stone.

Start with volume

Whatever the supplier quotes, work out your volume first. Same formula as any other material sold by depth:

cubic yards = (square feet × depth in inches) ÷ 324

A 4 foot wide path running 60 feet is 240 square feet. At 3 inches deep that is (240 × 3) ÷ 324 = 2.2 cubic yards.

Then convert to weight

tons = cubic yards × tons per cubic yard
cubic yards = tons ÷ tons per cubic yard

That middle number is density, and it is the whole reason the two units do not line up neatly. These are the figures the planner uses:

Material Tons per cubic yard A 2.2 yard path weighs
Gravel / crushed stone1.43.1 tons
Decomposed granite1.53.3 tons
River rock1.43.1 tons

Treat those as planning figures, not physics. Ask your supplier for theirs before a large order — on ten yards, a density that is off by 0.1 moves the bill by a full ton.

Why density moves

That last one cuts both ways, and it is the practical argument for buying by volume where you have the choice: a cubic yard is a cubic yard whatever the weather did.

How deep

Use Depth Notes
Decorative beds2 inOver fabric, mainly for looks
Walking paths2–3 inDeeper feels loose underfoot
Driveway surface4 inOn top of a compacted base, not on bare soil

A driveway is two layers, not one. The surface stone sits on a compacted base course, and the base is what actually carries the load — a thick layer of pretty stone straight onto soil will rut the first time something heavy parks on it.

Order extra for compaction

Crushed stone with fines in it compacts by roughly a fifth once it is rolled or plate tamped. So a finished 4 inch layer starts life about 5 inches loose, and your order should be based on the loose figure:

order ≈ compacted volume × 1.25

Clean rounded stone — pea gravel, river rock — barely compacts at all, so skip the allowance there and just add the usual 5–10% for spillage and uneven ground.

Before you call the supplier

Work out your volume in the planner

Paint the path or the drive, set the depth, and the totals panel gives you square feet, cubic yards and tons side by side — so whichever unit the supplier quotes in, you already have the number.